Home › Equipment Guides › Modular Gas Plants vs. Stick-Built Construction

Modular Gas Plants vs. Stick-Built Construction

Natural gas processing projects can be built in different ways. Some projects are well suited for modular gas plant fabrication, where major equipment, piping, structural steel, instrumentation, and controls are assembled into one or more modules before shipment. Other projects may require more field construction because of plant size, site layout, owner standards, local labor strategy, or transportation constraints.

The right approach depends on the application. A modular gas plant is not automatically the right answer for every facility, and stick-built construction is not automatically the wrong one. The decision should be based on process requirements, equipment scope, site conditions, fabrication requirements, schedule drivers, transportation limits, and the amount of work that should happen in the shop versus in the field.

QB Johnson manufactures custom natural gas processing equipment in Oklahoma City, including modular gas plants, dehydration equipment, treating equipment, separation equipment, heating equipment, and related process packages. This guide explains how modular and stick-built approaches compare so operators, engineers, EPC firms, and procurement teams can make a more practical project decision.

What Is a Modular Gas Plant?

A modular gas plant is a gas processing package built in modules or skids before it is transported to the project site. Depending on the application, a modular plant may include inlet separation, gas dehydration, amine treating, refrigeration, liquid recovery, heat exchange, pressure control, instrumentation, structural steel, interconnecting piping, and control systems.

The goal is to move as much practical work as possible into a controlled fabrication environment. Instead of building every major section in the field, the manufacturer can fabricate and assemble defined sections in a shop, inspect the work, document the package, and prepare the equipment for shipment.

Modular construction is commonly considered when a project needs:

  • More shop-controlled fabrication
  • Reduced field assembly where practical
  • Better definition of equipment scope before shipment
  • Repeatable project execution for similar applications
  • Integrated equipment packages built around a gas analysis and outlet specification
  • A way to coordinate multiple process steps within a defined package

For natural gas processing, modular design can be especially useful when the equipment scope combines multiple systems. A single project may include TEG dehydration units, amine treating units, molecular sieve dehydration, separators, filter separators, heaters, heat exchangers, and other process equipment. Building those systems into coordinated modules can simplify the interface between equipment types.

What Is Stick-Built Construction?

Stick-built construction means more of the plant is assembled at the project site. Equipment, piping, structural steel, electrical work, controls, insulation, and other systems are installed and connected in the field rather than being fully integrated into shop-built modules.

This approach can make sense for some projects. Very large plants, complex site tie-ins, unusual plot plans, remote installation constraints, owner-standardized construction programs, and projects with significant field-built infrastructure may all point toward a stick-built or hybrid approach.

Stick-built construction can also be appropriate when equipment sizes exceed practical module transportation limits, when local field labor is a central part of the project strategy, or when the owner wants to directly manage a large amount of site work.

For many gas processing projects, the decision is not purely modular or purely stick-built. A hybrid approach may be the best fit: major process equipment can be fabricated as modular packages while certain piping, utilities, foundations, interconnects, and site-specific systems are completed in the field.

How Modular Gas Plants Can Help

Modular gas plants can reduce some project risks when the application fits the modular approach. The main advantage is not a generic promise of lower cost or faster delivery. The advantage is that more work can be planned, fabricated, inspected, and documented before the equipment reaches the site.

That can help with several project areas.

Shop-Controlled Fabrication

In a shop environment, welding, fit-up, assembly, paint, instrumentation, QA/QC, and documentation can be managed with fewer of the variables that affect field construction. Weather, site congestion, access limitations, and field labor coordination can still matter, but more of the equipment package is completed before those site conditions become the primary constraint.

For projects that require ASME-code fabrication, pressure vessels, piping, structural steel, controls, and detailed documentation, a modular approach can give the project team a clearer view of the package before shipment.

Defined Equipment Interfaces

Gas processing equipment often depends on clean interfaces between systems. Inlet separation affects downstream dehydration and treating. Dehydration may affect refrigeration, liquid recovery, and outlet gas specifications. Heating, pressure control, and filtration may protect downstream equipment or support stable operation.

When those systems are designed together, the package can be built around the gas composition, flow rate, pressure, temperature, outlet requirements, site conditions, and applicable code requirements. Modular fabrication can help coordinate the physical and process interfaces between equipment types before field installation begins.

Reduced Field Assembly Where Practical

Field construction is still required for foundations, unloading, setting equipment, utility connections, site piping, electrical terminations, controls integration, commissioning, and startup. Modular construction does not eliminate field work.

It can, however, reduce the amount of process equipment assembly that has to happen at the site. For projects where field access, labor availability, weather, or schedule coordination are concerns, moving more work into the shop can be useful.

Documentation and Inspection

Gas processing equipment needs more than a good layout. It needs inspection records, drawings, material documentation, pressure vessel documentation, weld records, testing records, instrumentation details, and project-specific submittals.

When a modular gas plant is fabricated by a single equipment manufacturer, documentation can be organized around the package rather than scattered across many field-built interfaces. That does not remove the need for owner, EPC, or regulatory review, but it can make the equipment documentation easier to manage.

When Stick-Built Construction May Be the Better Fit

Stick-built construction remains a practical choice for many projects. It may be the better fit when the plant is too large for economical module transport, when the site has unusual constraints, or when the owner wants to integrate equipment into a larger field-built facility.

Stick-built construction may make sense for:

  • Very large gas processing facilities
  • Projects with extensive field piping or utilities
  • Sites with equipment access limitations
  • Facilities that require unusual equipment orientation or spacing
  • Projects with complex tie-ins to existing systems
  • Owner-managed construction programs
  • Projects where transportation limits make modularization impractical

In those cases, modular equipment may still play a role. A project can use shop-built dehydration, treating, separation, heating, or control packages while leaving large interconnecting systems and site-specific infrastructure for field construction.

Transportation and Site Considerations

Transportation is one of the most important practical limits in modular design. A module has to be engineered not only for operation, but also for lifting, loading, transport, unloading, and setting at the site.

The project team should review:

  • Module dimensions and weight
  • Highway, rail, barge, or ocean freight limitations
  • Permitting requirements for oversized loads
  • Lifting points and rigging plans
  • Site access roads and turning radius
  • Foundation and setting requirements
  • Field connections and tie-in locations
  • Weather exposure during shipment and storage

Transportation constraints do not necessarily prevent modular design, but they influence module size, layout, number of modules, and installation planning. A larger process plant may be divided into multiple modules, with field interconnects completed after setting.

Cost and Schedule Considerations

It is tempting to reduce the comparison to cost and schedule, but those numbers are project-specific. Modular construction can reduce some field labor, improve equipment scope definition, and support more controlled fabrication. Stick-built construction can be practical when local field resources, large equipment, or site-specific integration drive the project.

The real comparison should include:

  • Shop fabrication cost
  • Field labor and supervision
  • Transportation and heavy-haul requirements
  • Site preparation and foundations
  • Electrical, instrumentation, and controls integration
  • Weather and access risk
  • Inspection and documentation requirements
  • Startup and commissioning support
  • Change management during the project

For some projects, modularization can improve predictability because more of the equipment package is completed before it reaches the field. For other projects, transportation limits or site requirements may reduce that advantage. The best decision comes from reviewing the complete scope, not from assuming one construction method is always less expensive.

Quality and Fabrication Considerations

Quality is not determined by the word modular or stick-built. It is determined by engineering, fabrication standards, inspection practices, documentation, project control, and execution.

Modular fabrication can support quality by keeping more work in a controlled shop environment. That can be valuable for ASME-code pressure vessels, piping, welding, fit-up, instrumentation, coatings, and packaged equipment assembly. Stick-built work can also meet high standards when the field construction team, inspection process, and project controls are strong.

For QB Johnson projects, the practical question is how much of the gas processing system should be engineered, fabricated, assembled, inspected, and documented before shipment. That answer depends on the equipment scope, project specifications, and site conditions.

Modular Gas Plant Equipment Scope

A modular gas plant can include many types of natural gas processing and conditioning equipment. The exact scope depends on the gas stream and outlet requirements.

Common equipment may include:

  • Inlet separators or production separators
  • Filter separators for liquid and solids removal
  • TEG dehydration units for water vapor removal
  • Molecular sieve dehydration for very low outlet moisture requirements
  • Amine treating units for H2S and CO2 removal
  • Indirect line heaters or other heating equipment
  • Heat exchangers for process heat transfer
  • Refrigeration equipment or liquid recovery systems
  • Control panels, instrumentation, and process piping
  • Structural modules, platforms, access, and supports

Because each project is different, the equipment should be selected around the gas analysis, expected flow rate, operating pressure, inlet temperature, contaminants, outlet gas specification, liquid handling requirements, utilities, site conditions, and applicable code requirements.

How QB Johnson Approaches Modular Gas Plant Projects

QB Johnson designs and fabricates custom gas processing equipment around the application. The process starts with the project requirements: gas composition, flow rate, pressure, temperature, inlet contaminants, desired outlet specification, site conditions, and customer specifications.

From there, the equipment scope can be developed around the process. Some projects may only need a focused dehydration or separation package. Others may require a broader modular gas plant with treating, dehydration, separation, refrigeration, heating, liquid recovery, and integrated controls.

QB Johnson's Oklahoma City facilities support in-house engineering, ASME-code fabrication, QA/QC, paint, assembly, documentation, and project support. That in-house capability matters because modular gas plants are not catalog items. They have to be built around the project.

Modular vs. Stick-Built Decision Guide

Consider a modular gas plant when:

  • The process scope can be divided into transportable modules
  • Shop-controlled fabrication is valuable to the project
  • The owner wants more equipment assembly completed before site delivery
  • The project includes multiple integrated gas conditioning systems
  • Field labor, weather, or site access may create coordination challenges
  • Documentation and package-level inspection need to be tightly organized

Consider stick-built or hybrid construction when:

  • The facility is too large for practical modular transport
  • Site tie-ins and field infrastructure dominate the work
  • The owner wants to manage construction with field labor
  • Existing plant layout creates unusual access or orientation requirements
  • Transportation size or weight limits would make modularization inefficient
  • Large utilities, pipe racks, foundations, or electrical systems are field-driven

The best answer may be a hybrid package: modularize the process equipment that benefits from shop fabrication, then complete site-specific connections and infrastructure in the field.

Talk Through the Right Construction Approach

If you are comparing modular gas plant fabrication with stick-built construction, the right answer depends on the process, site, schedule, transportation, and equipment scope. Send QB Johnson your gas analysis, flow rate, pressure, temperature, outlet requirements, site conditions, and applicable project specifications.

 

QB Johnson can review the application and discuss whether a modular gas plant, a focused equipment package, or a hybrid approach makes sense for your project. You can also request a quote for a modular gas plant directly.